PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SAMARTH RESIDENCYMahaRERA P52100049691

by SHIVSAMARTH DEVELOPERS

SURVEY NO 9/3/4/2, ALANDI KHED, 412105

Dec 2025
Possession
81.8%
Built
0
Complaints
45
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 81.8%.

Official RERA facts

Registration
P52100049691
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
81.8% complete
Units sold
22 of 45

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Feb 2023
Floors
8
Unit mix
42 res ยท 3 comm
Architect
SK ASSOCIATES
Public authority
Alandi Municipal Council Office

Buyer community

Connect with other buyers and owners of SAMARTH RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAMARTH RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.