PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Kanishka Grand Plaza MaxMahaRERA P52100049982

by Platinum Lifespace Developers

S No 125/1/1 Saswad, Saswad, 412301

Dec 2026
Possession
0%
Built
0
Complaints
0
Units
Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 0%.

Official RERA facts

Registration
P52100049982
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
0% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2023
Floors
4

Buyer community

Connect with other buyers and owners of Kanishka Grand Plaza Max โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kanishka Grand Plaza Max. Real notes from real buyers beat any brochure.

Start a discussion