PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Rahul Downtown - Phase IIMahaRERA P52100050682

by Paras Multispace LLP

11/10/1, 11/11/1 to 11/11/10, 11/12, 11/13, Punawale, 411033

Apr 2027
Possession
51.5%
Built
1
Complaints
664
Units
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Apr 2027 per the RERA filing.

Official RERA facts

Registration
P52100050682
Status
New
Stage
Certificate Signed
Possession
April 2027originally December 2026
Construction
51.5% complete
Units sold
388 of 664

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Apr 2023
Floors
30
Unit mix
632 res ยท 32 comm
Architect
Pandit Joshi & Associates

Buyer community

Connect with other buyers and owners of Rahul Downtown - Phase II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Rahul Downtown - Phase II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.