Under construction

MANMOHAN RESIDENCYMahaRERA P52100050793

by HOME DEVELOPERS AND REALITY

SR NO 59, HISSA NO 2/51,+2/52,+2/53.+2/69,+2/78,+59/2/82,59/2/83, KONDHWA BK,PUNE 411048, PUNE, 411048

Dec 2025
Possession
86.5%
Built
0
Complaints
97
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 86.5%.

Official RERA facts

Registration
P52100050793
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
86.5% complete
Units sold
61 of 97

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths95%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)99%
Storm Water Drains99%
Street Lightingnot started
Water conservation /Rain water harvesting99%
Fire protection and fire safety requirements99%
Electrical meter room, sub-station, receiving station98%

Building & registration

RERA registered
May 2023
Floors
14
Unit mix
83 res ยท 14 comm
Architect
CUBIX ARCHITECTS

Buyer community

Connect with other buyers and owners of MANMOHAN RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MANMOHAN RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion