High risk
- Behind schedule. Possession is due Jun 2027 but construction is only at 46.1%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Promoter
Builder profile
DIVINE BUILDCON
View the promoter’s full developer profile and other projects under the same builder group.
Official RERA facts
- Registration
- P52100050928
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027
- Construction
- 46.1% complete
- Units sold
- 14 of 128
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- May 2023
- Floors
- 8
- Unit mix
- 110 res · 18 comm
Buyer community
Connect with other buyers and owners of NEWQUAY — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet — start one and connect with the next buyer researching NEWQUAY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities — what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.