Under construction

STATE BANK OF INDIA SNEHDEEP CHSL

by Kotibhaskar Infrastructures &Developers Pvt.Ltd.

Plot No. 8+9+10, Survey No. 19/1-B Out of CTS 668, Haveli, 411038

Sept 2026
Possession
81.8%
Built
0
Complaints
56
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52100051137
Status
New
Stage
Certificate Signed
Possession
September 2026originally March 2026
Construction
81.8% complete
Units sold
25 of 56

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
May 2023
Floors
15
Unit mix
56 res ยท 0 comm
Architect
ARCHLAND ARCHITECTS

Buyer community

Connect with other buyers and owners of STATE BANK OF INDIA SNEHDEEP CHSL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching STATE BANK OF INDIA SNEHDEEP CHSL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.