PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

NIRMAN HILLSIDEMahaRERA P52100051666

by MR GURURAJ NARSINHA JOSHI

SURVEY NO 7 HISSA NO 2A/4/5/6+7+8, DHANKAWADI-EXT, 411043

Jun 2027
Possession
70%
Built
0
Complaints
22
Units
High risk
  • Possession delayed ~1 yr. Originally promised Jan 2026, now proposed Jun 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52100051666
Status
New
Stage
Certificate Signed
Possession
June 2027originally January 2026
Construction
70% complete
Units sold
10 of 22

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2023
Floors
6
Unit mix
22 res ยท 0 comm

Buyer community

Connect with other buyers and owners of NIRMAN HILLSIDE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NIRMAN HILLSIDE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.