Under construction

MANTRA MESMER PHASE 6

by MANTRA ZIRCONIA PRIVATE LIMITED

S NO 9 TO 14 HISSA NO 1/52 & 1/53 P MUNDHWA KESHAVNAGAR PUNE, Haveli, 411036

Dec 2027
Possession
79.1%
Built
0
Complaints
44
Units
Caution
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100052535
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
79.1% complete
Units sold
36 of 44

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths55%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains70%
Landscaping & Tree Planting20%
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting50%
Energy managemcntnot started
Fire protection and fire safety requirements40%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2023
Floors
24
Unit mix
44 res ยท 0 comm
Architect
JAY AERAM & ASSOCIATES

Buyer community

Connect with other buyers and owners of MANTRA MESMER PHASE 6 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MANTRA MESMER PHASE 6. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.