Under construction

LA VISTAMahaRERA P52100052539

by DARSHANRAJ REALITY

SR. NO.134/1A/1 TO 12 CTS NO. 2712/1A/1, PLOT NO. 59, BHOSALE NAGAR, SHIVAJI NAGAR, 411007

Apr 2026
Possession
78.2%
Built
0
Complaints
9
Units
High risk
  • Possession date passed. The proposed possession date (Apr 2026) has passed with construction at 78.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2026 per the RERA filing.

Official RERA facts

Registration
P52100052539
Status
New
Stage
Certificate Signed
Possession
April 2026
Construction
78.2% complete
Units sold
1 of 9

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Sept 2023
Floors
7
Unit mix
9 res ยท 0 comm
Architect
SWAPNIL KSHIRSAGAR

Buyer community

Connect with other buyers and owners of LA VISTA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching LA VISTA. Real notes from real buyers beat any brochure.

Start a discussion