NB TOWERSMahaRERA P52100052677

by SHEKHAR INFRATECH

SECTOR NO 11, PLOT NO 148 D, NEAR TULSI LANDMARK, 412105

Jun 2026
Possession
79.8%
Built
0
Complaints
179
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 79.8%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2026 per the RERA filing.

Official RERA facts

Registration
P52100052677
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
79.8% complete
Units sold
115 of 179

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2023
Floors
23
Unit mix
157 res ยท 22 comm

Buyer community

Connect with other buyers and owners of NB TOWERS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NB TOWERS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.