Under construction

MONTREAL - A-B-C-DMahaRERA P52100053279

by CHARHOLI INFRASTRUCTURE LLP

S NO 138(part), 139(part), CHARHOLI PCMC, 412105

Dec 2027
Possession
50.1%
Built
0
Complaints
448
Units
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100053279
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
50.1% complete
Units sold
431 of 448

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)6%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Oct 2023
Floors
31
Unit mix
448 res ยท 0 comm
Architect
AVINASH PATIL & ASSOCIATES

Buyer community

Connect with other buyers and owners of MONTREAL - A-B-C-D โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MONTREAL - A-B-C-D. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.