Under construction

Anandtara DyankunjMahaRERA P52100053321

by Aanandtara properties

41/10B, Keshavnagar, 411036

Jul 2027
Possession
15.8%
Built
0
Complaints
11
Units
High risk
  • Behind schedule. Possession is due Jul 2027 but construction is only at 15.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jul 2027 per the RERA filing.

Official RERA facts

Registration
P52100053321
Status
New
Stage
Certificate Signed
Possession
July 2027
Construction
15.8% complete
Units sold
4 of 11

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2023
Floors
4
Unit mix
11 res ยท 0 comm
Architect
GIRISH MANE

Buyer community

Connect with other buyers and owners of Anandtara Dyankunj โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Anandtara Dyankunj. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.