All RERA projects
๐๏ธ
Under construction
ML TowerMahaRERA P52100053327
by BML Builders
Survey No. 97/1A/1A/15 Ravet Pune 412101, Pune, 421101
Jan 2027
Possession
74.7%
Built
0
Complaints
53
Units
Caution
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2027 per the RERA filing.
Official RERA facts
- Registration
- P52100053327
- Status
- New
- Stage
- Certificate Signed
- Possession
- January 2027originally July 2026
- Construction
- 74.7% complete
- Units sold
- 38 of 53
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply40%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvesting80%
Energy managemcnt50%
Fire protection and fire safety requirements70%
Electrical meter room, sub-station, receiving station60%
Open Parkingnot started
Building & registration
- RERA registered
- Oct 2023
- Floors
- 8
- Unit mix
- 20 res ยท 33 comm
- Architect
- Shamal Kavatkar
Buyer community
Connect with other buyers and owners of ML Tower โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching ML Tower. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.