SIDDH AMARA PHASE IIMahaRERA P52100053624

by Siddh Housing

57/3/1 to 57/3/16 + 1/1 Bawdhan, -, 411021

Dec 2026
Possession
72%
Built
0
Complaints
28
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52100053624
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
72% complete
Units sold
17 of 28

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station70%

Building & registration

RERA registered
Nov 2023
Floors
4
Unit mix
28 res ยท 0 comm
Architect
Prakash Kulkarni

Buyer community

Connect with other buyers and owners of SIDDH AMARA PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SIDDH AMARA PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.