PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Audumbar Green A WingMahaRERA P52100054752

by Alankar Bagal Group

S. No./Gat No. 27/1A/1 (P), Near Nimbalkar Nagar, Opp to Tata Steel Yard, Tathawade, Tal Mulshi, Dist. Pune 411033, Near Nimbalkar Nagar, Tathwade, 411033

Oct 2026
Possession
27.3%
Built
0
Complaints
35
Units
High risk
  • Behind schedule. Possession is due Oct 2026 but construction is only at 27.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.

Official RERA facts

Registration
P52100054752
Status
New
Stage
Certificate Signed
Possession
October 2026originally April 2026
Construction
27.3% complete
Units sold
0 of 35

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

RAMESH MAHADU KUMBHAR, SURESH MAHADU KUMBHAR, SOMNATH MAHADU KUMBHAR

Possession extension history

  • EA01062621178Revised to October 2026

    The project could not be completed within the stipulated validity period due to circumstances beyond our control, including technical issues in the execution process, shortage of labour during the construction period, and financial difficulties faced by the developer. These unavoidable challenges have caused delays in timely completion of the project.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2024
Floors
8
Unit mix
28 res ยท 7 comm
Architect
Makarand Ittam
Plot / CTS / survey no.
S. No./Gat No. 27/1A/1 (P), Near Nimbalkar Nagar, Opp to Tata Steel Yard, Tathawade, Tal Mulshi, Dist. Pune 411033
Planning authority
Pimpri Chinchwad Municipal Corporation
Approved layout land
1,700 sq.m
Land for this registration
1,700 sq.m
Permissible built-up area
1,396.71 sq.m
Registered office
Alankar Niwas
Plot boundaries
North
By remaining property fromSurvey No 27
South
By remaining property fromSurvey No 27
East
By Road and Survey No 25
West
By remaining property fromSurvey No 27
Parking
40 two-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • BANK OF BARODA โ€” 3441
    IFSC BARB0AKURDI
    NEW ADMINISTRATIVE BUILDING PCNTDA NEAR AKURDI RAILWAY STATION AKURDI PUNE MAHARASTRA 411044

Commencement Certificate documents

  • Commencement Certificate.pdf
  • Commencement.pdf
  • Commencement.pdf
  • Commencement.pdf
  • Commencement.pdf

Buyer community

Connect with other buyers and owners of Audumbar Green A Wing โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Audumbar Green A Wing. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.