Under construction

MORYA PARKMahaRERA P52100054837

by GAJDANT CONSTRUCTIONS LLP

SR.NO.68/2/B/2/2/1,2,3, SASWAD, 412301

Dec 2027
Possession
39.4%
Built
0
Complaints
158
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52100054837
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
39.4% complete
Units sold
33 of 158

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started

Building & registration

RERA registered
Feb 2024
Floors
11
Unit mix
148 res ยท 10 comm
Architect
vishal kumbharkar

Buyer community

Connect with other buyers and owners of MORYA PARK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MORYA PARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.