PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Kakkad OneworldMahaRERA P52100055312

by Kakkad Erectors LLP

Sr. No. 6/7+6/8+11/1(P)+11/6+11/7 BALEWADI, Balewadi, 411045

Dec 2028
Possession
6.4%
Built
0
Complaints
43
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52100055312
Status
New
Stage
Certificate Signed
Possession
December 2028
Construction
6.4% complete
Units sold
1 of 43

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Mar 2024
Floors
32 (sanctioned 18)
Unit mix
0 res ยท 43 comm

Buyer community

Connect with other buyers and owners of Kakkad Oneworld โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kakkad Oneworld. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.