Under construction

HIGHLIFE SURVEY NO 56/3/37/1P , 56/3/26/3 AT WADGAONSHERIMahaRERA P52100056118

by RM GROUP

56, Stella Maris School, 411014

Dec 2026
Possession
33.2%
Built
0
Complaints
34
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 33.2%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100056118
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
33.2% complete
Units sold
3 of 34

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Community Buildingsnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
May 2024
Floors
9
Unit mix
24 res ยท 10 comm

Buyer community

Connect with other buyers and owners of HIGHLIFE SURVEY NO 56/3/37/1P , 56/3/26/3 AT WADGAONSHERI โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching HIGHLIFE SURVEY NO 56/3/37/1P , 56/3/26/3 AT WADGAONSHERI. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.