The HillfrontMahaRERA P52100076591
Survey No. 6/1/1, Plot no. 3, Baner, 411045
Nov 2026
Possession
28.5%
Built
0
Complaints
28
Units
High risk
- Behind schedule. Possession is due Nov 2026 but construction is only at 28.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2026 per the RERA filing.
Official RERA facts
- Registration
- P52100076591
- Status
- New
- Stage
- Certificate Signed
- Possession
- November 2026
- Construction
- 28.5% complete
- Units sold
- 8 of 28
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Jun 2024
- Floors
- 8
- Unit mix
- 28 res ยท 0 comm
Buyer community
Connect with other buyers and owners of The Hillfront โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching The Hillfront. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.