OPULENT TOWERMahaRERA P52100077241

by MAHESHWARI LANDMARK

Sr No 139/2/2/3, 139/2/2/1, Ravet, 412101

Jun 2027
Possession
40%
Built
0
Complaints
54
Units
High risk
  • Behind schedule. Possession is due Jun 2027 but construction is only at 40%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P52100077241
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
40% complete
Units sold
7 of 54

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2024
Floors
7
Unit mix
44 res ยท 10 comm
Architect
DEEPAK PATIL

Buyer community

Connect with other buyers and owners of OPULENT TOWER โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching OPULENT TOWER. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.