PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Crystal HillsMahaRERA P52100077295

by Anand Developers

Plot No D-15, S No 94/1, 95, 96/1/1, 96/1/2, 96/2, 96/3, 96/4, 97, Mohannagar Co-operative Housing Society Ltd, 411045

Mar 2025
Possession
0%
Built
0
Complaints
14
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2025 per the RERA filing.

Official RERA facts

Registration
P52100077295
Status
New
Stage
Certificate Signed
Possession
March 2025
Construction
0% complete
Units sold
13 of 14

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2024
Floors
7
Unit mix
14 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Crystal Hills โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Crystal Hills. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.