Sarita Niketan
by Manjari Housing Projects LLP
159 part, 160 part, Manjari-Khurd, 412307
No delays, complaints or enforcement actions in the official disclosures we track.
Official RERA facts
- Registration
- P52100079924
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2028originally December 2027
- Construction
- 43.3% complete
- Units sold
- 0 of 476
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EA10012619392Revised to December 2028
The project consist of 1 sanctioned building with 25 sanctioned floors. The project is presently in its execution stage of completion. We are currently engaged in completing RCC works. The delay in completing the RCC works has been caused by various factors. These factors had a cascading effect on the commencement of the finishing activities of lower floors. d. The situation remained difficult despite our best efforts to address these problems, such as our attempt to retain labour on-site. Now that the RCC activities have started to be executed in a timely fashion we are optimistic that we would also be able to execute finishing activities at the required pace for executed floors. However, due to delays seen in the past as mentioned above, we are now required to update the project's completion schedule and request an extension till 15-12-2028. e. Additionally, we wish to inform you that there are NO SOLD UNITS as on date. Neither any commitments to customers have been made nor the any booking amount has been received. We intend to execute an agreement with the customer to mention the date of possession on or before 15-12-2028. Kindly process our application and grant us the extension till 15-12-2028. After careful consideration of the current circumstances and the challenges faced, we propose a revised completion timeline. We expect the project to be completed within 15-12-2028. That till date, no application for extension of the project registration has ever been made or granted. The present application is the first and last application seeking extension under Section 6 of the Real Estate (Regulation and Development) Act, 2016. That the present extension is sought for a period less than twelve (12) months, and the revised proposed date of completion for the project is 15-12-2028. We kindly request you to consider our application for an extension under Section 6 of MAHARERA, considering the circumstances explained above and the supporting documents provided. We assure you to expedite the project's completion and comply with all the applicable provisions of MAHARERA.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Apr 2025
- Floors
- 25
- Unit mix
- 476 res ยท 0 comm
- Architect
- ANA Consortium Pvt Ltd
- Plot / CTS / survey no.
- 159 part, 160 part
- Planning authority
- Pune Metropolitan Region Development Authority
- Approved layout land
- 5,202 sq.m
- Land for this registration
- 5,202 sq.m
- Recreational open space
- 520.2 sq.m
- Permissible built-up area
- 24,375.16 sq.m
- Registered office
- Godrej One
- North
- Adj gat no 159
- South
- 18m wide road
- East
- 9m wide road
- West
- 18m wide road
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 62299IFSC ICIC0000321ICICI Bank Ltd., Shop No. 7,8,9 & 10, Empire Square, City Survey No. 4746, Next to Auto Cluster, Off Pune Mumbai Highway, Chinchwad, Pune, Maharashtra - 411019
Commencement Certificate documents
- Updated Annexure F.pdf
- Commencement Certificate-compressed.pdf
Buyer community
Connect with other buyers and owners of Sarita Niketan โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Sarita Niketan. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.