PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Sarita Niketan

MahaRERA P52100079924Clean record

by Manjari Housing Projects LLP

159 part, 160 part, Manjari-Khurd, 412307

Official record
Dec 2028
Possession
43.3%
Built
0
Complaints
476
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52100079924
Status
New
Stage
Certificate Signed
Possession
December 2028originally December 2027
Construction
43.3% complete
Units sold
0 of 476

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EA10012619392Revised to December 2028

    The project consist of 1 sanctioned building with 25 sanctioned floors. The project is presently in its execution stage of completion. We are currently engaged in completing RCC works. The delay in completing the RCC works has been caused by various factors. These factors had a cascading effect on the commencement of the finishing activities of lower floors. d. The situation remained difficult despite our best efforts to address these problems, such as our attempt to retain labour on-site. Now that the RCC activities have started to be executed in a timely fashion we are optimistic that we would also be able to execute finishing activities at the required pace for executed floors. However, due to delays seen in the past as mentioned above, we are now required to update the project's completion schedule and request an extension till 15-12-2028. e. Additionally, we wish to inform you that there are NO SOLD UNITS as on date. Neither any commitments to customers have been made nor the any booking amount has been received. We intend to execute an agreement with the customer to mention the date of possession on or before 15-12-2028. Kindly process our application and grant us the extension till 15-12-2028. After careful consideration of the current circumstances and the challenges faced, we propose a revised completion timeline. We expect the project to be completed within 15-12-2028. That till date, no application for extension of the project registration has ever been made or granted. The present application is the first and last application seeking extension under Section 6 of the Real Estate (Regulation and Development) Act, 2016. That the present extension is sought for a period less than twelve (12) months, and the revised proposed date of completion for the project is 15-12-2028. We kindly request you to consider our application for an extension under Section 6 of MAHARERA, considering the circumstances explained above and the supporting documents provided. We assure you to expedite the project's completion and comply with all the applicable provisions of MAHARERA.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Apr 2025
Floors
25
Unit mix
476 res ยท 0 comm
Architect
ANA Consortium Pvt Ltd
Plot / CTS / survey no.
159 part, 160 part
Planning authority
Pune Metropolitan Region Development Authority
Approved layout land
5,202 sq.m
Land for this registration
5,202 sq.m
Recreational open space
520.2 sq.m
Permissible built-up area
24,375.16 sq.m
Registered office
Godrej One
Plot boundaries
North
Adj gat no 159
South
18m wide road
East
9m wide road
West
18m wide road
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • ICICI BANK LIMITED โ€” 62299
    IFSC ICIC0000321
    ICICI Bank Ltd., Shop No. 7,8,9 & 10, Empire Square, City Survey No. 4746, Next to Auto Cluster, Off Pune Mumbai Highway, Chinchwad, Pune, Maharashtra - 411019

Commencement Certificate documents

  • Updated Annexure F.pdf
  • Commencement Certificate-compressed.pdf

Buyer community

Connect with other buyers and owners of Sarita Niketan โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Sarita Niketan. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.