CHAKAN NAGARPARISHAD PMAY AHP
GAT NO 818 (P), CHAKAN, 410501
- Behind schedule. Possession is due Dec 2026 but construction is only at 0%.
- Promised amenities not started. Gymnasium, Landscaped Garden are at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52100080338
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 0% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- May 2025
- Floors
- 8
- Plot / CTS / survey no.
- GAT NO 818 (P)
- Planning authority
- Others
- Approved layout land
- 20,000 sq.m
- Land for this registration
- 20,000 sq.m
- Recreational open space
- 1,939.11 sq.m
- Permissible built-up area
- 9,810.1 sq.m
- Registered office
- DIVYAJOYTI
- North
- GAT NO 761
- South
- GAT NO 819 820
- East
- GAT NO 818
- West
- GAT NO 757
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- BANK OF MAHARASHTRA โ 91145IFSC MAHB0001151PARDESHI BUILDING, MARKET YARD CHAKAN TAL KHED DIST PUNE 410501
Commencement Certificate documents
- Building Permission.pdf
Buyer community
Connect with other buyers and owners of CHAKAN NAGARPARISHAD PMAY AHP โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching CHAKAN NAGARPARISHAD PMAY AHP. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.