CASA BONITA
by CASA BONITA CONSTRUCTION LLP
plot no 7 & 8 , Sr. No. 32/1A/2, Baner, 411045
- Possession delayed ~1 yr. Originally promised Jul 2027, now proposed Dec 2028 per the RERA filing.
Official RERA facts
- Registration
- P52100080631
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2028originally July 2027
- Construction
- 8.8% complete
- Units sold
- 0 of 20
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EA10032620155Revised to December 2028
Due to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/12/2028 to complete the project
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jun 2025
- Floors
- 6
- Unit mix
- 20 res ยท 0 comm
- Plot / CTS / survey no.
- plot no 7 & 8 , Sr. No. 32/1A/2
- Planning authority
- .
- Approved layout land
- 1,036 sq.m
- Land for this registration
- 1,036 sq.m
- Recreational open space
- 0 sq.m
- Permissible built-up area
- 4,748.96 sq.m
- Registered office
- B1/11
- North
- Sr No 32 Part 1A Part 2 Plot No 6
- South
- Sr No 32 Part 1A Part 2 Plot No 9
- East
- 9 Mtrs Colony Road
- West
- Sr No 32
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- STATE BANK OF INDIA โ 112662IFSC SBIN0000575Pimpri Branch ,Opp Kalasagar Hotel Kasarwadi P B No 1 Pune-411034
Commencement Certificate documents
- Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of CASA BONITA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching CASA BONITA. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.