PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

The Courtyard Phase-I Building E and CMahaRERA P52200000247

by Marc Developers

GLR Sy No 3, Tarakpur, 414003

Mar 2019
Possession
90.9%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 90.9%.

Official RERA facts

Registration
P52200000247
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Water conservation /Rain water harvestingdone
Water conservation /Rain water harvestingnot started
Energy managemcntdone
Energy managemcntnot started
Fire protection and fire safety requirementsdone
Fire protection and fire safety requirementsnot started
Open Parkingnot started
Club Housedone
Solar Water Heaterdone

Building & registration

RERA registered
Jul 2017
Floors
10

Buyer community

Connect with other buyers and owners of The Courtyard Phase-I Building E and C โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching The Courtyard Phase-I Building E and C. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.