PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

UJWAL DHAMMahaRERA P52400015317

by NIWARA GRUHNIRMAN PVT LTD

PLOT NO 16 SY NO 157, Latur (M Cl), 413512

Dec 2018
Possession
9.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2018) has passed with construction at 9.8%.

Official RERA facts

Registration
P52400015317
Status
Ongoing
Stage
Certificate Signed
Possession
December 2018
Construction
9.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths20%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Feb 2018
Floors
3

Buyer community

Connect with other buyers and owners of UJWAL DHAM โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching UJWAL DHAM. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.