Under construction
VEER KOHINOOR TOWERMahaRERA P52600019433
PLOT NO. A-10, NEW S.NO. 108/2, SONIYA NAGAR, 413005
Jul 2026
Possession
10.7%
Built
0
Complaints
24
Units
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Jul 2026 per the RERA filing.
- Behind schedule. Possession is due Jul 2026 but construction is only at 10.7%.
Official RERA facts
- Registration
- P52600019433
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2026originally December 2024
- Construction
- 10.7% complete
- Units sold
- 20 of 24
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements10%
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Building & registration
- RERA registered
- Jan 2019
- Floors
- 7
- Unit mix
- 14 res ยท 10 comm
- Architect
- Suresh Ambadas Mitthakol
Buyer community
Connect with other buyers and owners of VEER KOHINOOR TOWER โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching VEER KOHINOOR TOWER. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance