INDRADHANU PARKMahaRERA P52700002422
GST NO 263 PART, village bopardi, 412803
Nov 2025
Possession
68.8%
Built
0
Complaints
28
Units
High risk
- Possession delayed ~2 yrs. Originally promised Jan 2024, now proposed Nov 2025 per the RERA filing.
- Possession date passed. The proposed possession date (Nov 2025) has passed with construction at 68.8%.
Official RERA facts
- Registration
- P52700002422
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- November 2025originally January 2024
- Construction
- 68.8% complete
- Units sold
- 15 of 28
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Aggregate area of recreational Open Spacedone
Building & registration
- RERA registered
- Aug 2017
- Floors
- 2
- Unit mix
- 28 res ยท 0 comm
- Architect
- ANAND a KULKARNI
Buyer community
Connect with other buyers and owners of INDRADHANU PARK โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching INDRADHANU PARK. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.