WAI GREENS 2MahaRERA P52700004937

by SHREEJI HABITAT LLP

Gat No. 1043/2/2 Plot No. 1, Wai, 415516

Dec 2026
Possession
50.5%
Built
22
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Jul 2022, now proposed Dec 2026 per the RERA filing.
  • 22 RERA complaints. 22 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52700004937
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally July 2022
Construction
50.5% complete
Units sold
0 of 0

RERA complaint record22 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
8

Buyer community

Connect with other buyers and owners of WAI GREENS 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching WAI GREENS 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.