- Possession delayed ~1 yr. Originally promised Nov 2025, now proposed Mar 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P52700029745
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally November 2025
- Construction
- 62.5% complete
- Units sold
- 33 of 78
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
SHREE VIHAR
Possession extension history
- EA27022620041Revised to March 2027
Due to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/03/2027 to complete the project
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jun 2021
- Floors
- 7
- Unit mix
- 78 res ยท 0 comm
- Plot / CTS / survey no.
- 187/2
- Planning authority
- SATARA NAGAR PARISHAD, SATARA
- Approved layout land
- 2,400 sq.m
- Land for this registration
- 2,400 sq.m
- Permissible built-up area
- 5,224.28 sq.m
- Registered office
- BAND PLAZA
- North
- ROAD
- South
- PLOT NO 188
- East
- PLOT NO 187 3
- West
- PLOT NO 187 3
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- DOMBIVLI NAGARI SAHAKARI BANK LIMITED โ 43413IFSC DNSB0000066MOTI CHOWK SATAR
Commencement Certificate documents
- PERMTION.pdf
Buyer community
Connect with other buyers and owners of SHREE VIHAR โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHREE VIHAR. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.