Under construction

CHAITANYA DHAMMahaRERA P52700030902

by RAPID DEVELOPERS

380/7/1 PLOT NO 1/2/3, -, 415002

Aug 2026
Possession
90.9%
Built
0
Complaints
24
Units
Caution
  • Possession delayed ~1 yr. Originally promised Mar 2025, now proposed Aug 2026 per the RERA filing.

Official RERA facts

Registration
P52700030902
Status
New
Stage
Certificate Signed
Possession
August 2026originally March 2025
Construction
90.9% complete
Units sold
17 of 24

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EA12012619411Revised to August 2026

    Project is completed in all aspect. The Compleition Certificate issued by Satara Municipal Council 49 days late. So applied for Extension of Project. Completion Certificate is attached in other Documents

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Sewerage (Chamber, Lines, Septic Tank , STP)done
Treatment And Disposal Of Sewage And Sullage Waterdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Sept 2021
Floors
8
Unit mix
24 res ยท 0 comm
Architect
DHANANJAY INAMDAR
Plot / CTS / survey no.
380/7/1 PLOT NO 1/2/3
Planning authority
Satara Municipal Council
Approved layout land
458.89 sq.m
Land for this registration
458.89 sq.m
Permissible built-up area
1,390.82 sq.m
Registered office
OM RESIDENCY
Plot boundaries
North
9 MTRS WIDE ROAD
South
S NO 381
East
S NO 381-5
West
OPEN SPACE
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • THE KALYAN JANATA SAHAKARI BANK LTD. โ€” 84637
    IFSC KJSB0000203
    SATARA

Commencement Certificate documents

  • Comansment Order-min.pdf
  • RCC.pdf

Buyer community

Connect with other buyers and owners of CHAITANYA DHAM โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching CHAITANYA DHAM. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.