PropPin
High risk
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 28.2%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Mar 2025 per the RERA filing.

Promoter

Builder profile

Builder
Shriram Developers Satara

View the promoter’s full developer profile and other projects under the same builder group.

No other projects are linked to this promoter yet.

Official RERA facts

Registration
P52700032457
Status
New
Stage
Certificate Signed
Possession
March 2025originally November 2024
Construction
28.2% complete
Units sold
0 of 0