Under construction

Samarth Orchid

MahaRERA P52800025686High risk

by Shree Samarthkrupa Builders & Developers

Survey No. 29A1A11A1E1C, 291A1A1A1A23 and 291A1A2, and CTS No 2310 to 2313, Dapoli Camp, 415712

Official record
Dec 2026
Possession
82.3%
Built
0
Complaints
75
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2025, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52800025686
Status
New
Stage
Certificate Signed
Possession
December 2026originally June 2025
Construction
82.3% complete
Units sold
46 of 75

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

Vikas Anant Shintre

Possession extension history

  • EA22072502122Revised to December 2026

    The delay in project completion is primarily due to unforeseen natural disasters such as cyclones and floods, which significantly disrupted construction activities. Additionally, unfavorable market conditions and the unavailability of skilled labor further impacted the progress of the project. These cumulative challenges caused substantial delays beyond our control.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2020
Floors
6
Unit mix
53 res ยท 22 comm
Architect
Ravindra Mahadeo Patil
Plot / CTS / survey no.
Survey No. 29A1A11A1E1C, 291A1A1A1A23 and 291A1A2, and CTS No 2310 to 2313
Planning authority
Dapoli Nagarpanchayat Dapoli
Approved layout land
1,741 sq.m
Land for this registration
1,741 sq.m
Permissible built-up area
3,884.73 sq.m
Registered office
Shree Samarth Gruh Sankul
Plot boundaries
North
CTS No 2315 and Road
South
CTS No 22 and CTS No 2309
East
CTS No 2305
West
Dapoli Dabhol Road
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • BANK OF INDIA โ€” 22791
    IFSC BKID0WAINGB
    House No 1907 Mangalmurti Nivas At Post Jalgaon Taluka Dapoli District Ratnagiri Pincode 415712

Commencement Certificate documents

  • Commencement Certificate.pdf
  • New Commencement.pdf

Buyer community

Connect with other buyers and owners of Samarth Orchid โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Samarth Orchid. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.