PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SADGURU RESIDENCY

MahaRERA P52800026019Caution

by SAI DATTA BUILDERS AND DEVELOPERS LLP

69, -, 415709

Official record
Jun 2023
Possession
66.4%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 66.4%.

Official RERA facts

Registration
P52800026019
Status
New
Stage
Certificate Signed
Possession
June 2023
Construction
66.4% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2020
Floors
5
Plot / CTS / survey no.
69
Planning authority
Others
Approved layout land
1,800 sq.m
Land for this registration
1,800 sq.m
Recreational open space
1,800 sq.m
Permissible built-up area
1,761.04 sq.m
Registered office
SHREE SADGURU KRUPA
Plot boundaries
North
359 AND 360 AND GRAMPANCHAYAT ROAD
South
4 AND 5
East
68
West
358

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • ICICI BANK LIMITED โ€” 67899
    IFSC ICIC0006983
    SHOP NO 9 SHREE SADGURU KRUPA RAJARAM PATIL NAGAR ADIVALI NEAR KAKA DHABA KALYAN THANE KALYAN

Commencement Certificate documents

  • Construction Permission.pdf

Buyer community

Connect with other buyers and owners of SADGURU RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SADGURU RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.