- Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2023 per the RERA filing.
Official RERA facts
- Registration
- P52800045777
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2023
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
FAIZAL ABDUL REHMAN SHIVKAR, WASEEM ABDUL RAZZAQUE LAMBATE
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jun 2022
- Floors
- 5
- Plot / CTS / survey no.
- SURVEY NO 278/A/1/2/A/4 CTS NO-3212/3
- Planning authority
- Others
- Approved layout land
- 758 sq.m
- Land for this registration
- 758 sq.m
- Permissible built-up area
- 906.35 sq.m
- Registered office
- N S VIEW BUILDING
- North
- CTS NO 3212-2 PLOT NO 2
- South
- CTS NO 3212-6 PLOT NO 5
- East
- MUNICIPAL LAYOUT ROAD
- West
- CTS NO 3212-1
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- AXIS BANK โ 164271IFSC UTIB0004721KHARGHAR NAVI MUMBAI 410210
Commencement Certificate documents
- COMM CER.pdf
Buyer community
Connect with other buyers and owners of RIDA RESIDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching RIDA RESIDENCY. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.