BUTLER COMPLEX
Gut No. 26/9, Shringartali, 415724
- Behind schedule. Possession is due Dec 2026 but construction is only at 40%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52800055017
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 40% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Feb 2024
- Floors
- 5
- Plot / CTS / survey no.
- Gut No. 26/9
- Planning authority
- Others
- Approved layout land
- 1,500 sq.m
- Land for this registration
- 1,500 sq.m
- Permissible built-up area
- 1,498.32 sq.m
- Promoter contact
- Noor Mohammed Abbas Boat
- Registered office
- Butler Complex
- North
- Hissa No 11
- South
- Hissa no 8
- East
- Hissa No 10
- West
- Internal Road
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- CANARA BANK โ 37937IFSC CNRB0015374Patpanhale Shringartali Taluka Guhagar District Ratnagiri 415724
Commencement Certificate documents
- Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of BUTLER COMPLEX โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching BUTLER COMPLEX. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.