SAMRUDDHI APARTMENTMahaRERA P52900004545
25A2/15, Deulwadi, 416520
Oct 2018
Possession
53.9%
Built
0
Complaints
0
Units
Caution
- Possession date passed. The proposed possession date (Oct 2018) has passed with construction at 53.9%.
Official RERA facts
- Registration
- P52900004545
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2018
- Construction
- 53.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Water conservation /Rain water harvesting50%
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 4
Buyer community
Connect with other buyers and owners of SAMRUDDHI APARTMENT โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SAMRUDDHI APARTMENT. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.