Dec 2026
Possession
76.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Dec 2018, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52900005744
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2018
Construction
76.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supply30%
Sewerage (Chamber, Lines, Septic Tank , STP)64%
Storm Water Drains81%
Landscaping & Tree Planting47%
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of ASHWAMEDH โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ASHWAMEDH. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.