Under construction

PALKAR RESIDANCYMahaRERA P52900008832

by Sandeep Balkrishna Walavalkar

Survey No 167 Hissa No 12, Kankavali, 416602

Dec 2021
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 81.8%.

Official RERA facts

Registration
P52900008832
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021originally December 2019
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Aug 2017
Floors
3

Buyer community

Connect with other buyers and owners of PALKAR RESIDANCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PALKAR RESIDANCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.