SHREE TULJABHAVANI RESEDENCYMahaRERA P52900010546

by MANGESH RAJARAM MANKAR

29 1/ 1 B, Wayari, 416606

Nov 2018
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Nov 2018) has passed with construction at 90.9%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2018 per the RERA filing.

Official RERA facts

Registration
P52900010546
Status
Ongoing
Stage
Certificate Signed
Possession
November 2018
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingnot started
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of SHREE TULJABHAVANI RESEDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHREE TULJABHAVANI RESEDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.