Under construction
AXIS BLUESMahaRERA P52900021725
by EEJAK HOLDINGS PRIVATE LIMITED
432, 433,438,439, 446, 447, Yog Resort, 416512
Dec 2027
Possession
59%
Built
10
Complaints
128
Units
High risk
- Possession delayed ~3 yrs. Originally promised Jul 2024, now proposed Dec 2027 per the RERA filing.
- 10 RERA complaints. 10 complaint records are disclosed against this project on MahaRERA.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P52900021725
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally July 2024
- Construction
- 59% complete
- Units sold
- 105 of 128
RERA complaint record10 records
- ComplaintCC1260442216 Jul 2026Deepa Patil vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC126033591 Jun 2026Mahesh Rampur vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC1260321028 May 2026Viddhesh Hanumant Belgaonkar vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC1260310825 May 2026Gibin Gipson George vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC1260304923 May 2026Colleta Ruby Vaz vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC1260294319 May 2026Azaz Nizamuddin Khan vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC1260275711 May 2026Thudukurthi Prasanth Kumar vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC126026507 May 2026SITA PRABHU DESSAI vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC1260089218 Feb 2026Nidhi Mishra vs EEJAK HOLDINGS PRIVATE LIMITED
- ComplaintCC125018606 Jun 2025VINCENT LEWIS vs EEJAK HOLDINGS PRIVATE LIMITEDroznama 21- Disposed Off on consent term SIGNED.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Building & registration
- RERA registered
- Jul 2019
- Floors
- 5
- Unit mix
- 121 res ยท 7 comm
Buyer community
Connect with other buyers and owners of AXIS BLUES โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AXIS BLUES. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.