Avdhoot Chintan

MahaRERA P52900029041High risk

by Shashikant Shamrao Jadhav

Survey No 71 Hissa No 1/23 and Hissa No 1/24 Plot No 23 and 24, Sangirde, 416520

Official record
Mar 2023
Possession
52.2%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 52.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2023 per the RERA filing.

Official RERA facts

Registration
P52900029041
Status
New
Stage
Certificate Signed
Possession
March 2023
Construction
52.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Possession extension history

  • EXT52900015402Revised to September 2023

    Respected Sir, I, Shashikant Shamrao Jadhav, is executing the above referred real estate project. The date of completion as mentioned in the Application for RERA registration certificate was March 31, 2023. The Project construction is fully completed and Project Architect has given Completion Certificate for Purpose of getting occupancy certificate from Local Authority- Kudal Nagarpanchayat. We have already submitted a complete application to Kudal Nagarpanchayat for Purpose of granting occupancy certificate for the project. Since project is already completed with committed amenities along external development works , we will very soon get the occupancy certificate from local authority. The Copy of Architect’s completion certificate is attached with this application and application for granting occupancy certificate is submitted on BPMS Portal of Mahavastu.maharashtra.gov.in vide application no NPKUL/2023/158491/27533 for full occupancy. Hence, we request you to kindly allow extension of Completion date of project to September 30, 2023 and issue revised RERA registration certificate.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Apr 2021
Floors
9
Plot / CTS / survey no.
Survey No 71 Hissa No 1/23 and Hissa No 1/24 Plot No 23 and 24
Planning authority
Others
Approved layout land
742 sq.m
Land for this registration
742 sq.m
Permissible built-up area
2,237 sq.m
Promoter contact
Shashikant Shamrao Jadhav
Registered office
Sanman
Plot boundaries
North
Survey No 72 Hissa No 1
South
Internal Road
East
Survey No 70
West
Survey No 71 Hissa No 22 Plot No 22
Parking

Project bank account

The RERA-designated account this project's payments should go to — verify before wiring any money.

  • ICICI BANK LIMITED — 63195
    IFSC ICIC0001225
    Shop No 7, Bharat Arch, Andheri West, Mumbai, 400058

Commencement Certificate documents

  • Commencement Certificate.pdf

Buyer community

Connect with other buyers and owners of Avdhoot Chintan — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching Avdhoot Chintan. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.