- Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P52900031412
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2025
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Oct 2021
- Floors
- 6
- Plot / CTS / survey no.
- 1714 1717 1718 1719 1720 1721 4388
- Planning authority
- Others
- Approved layout land
- 2,042.6 sq.m
- Land for this registration
- 2,042.6 sq.m
- Permissible built-up area
- 3,449.78 sq.m
- Promoter contact
- Muralidhar Vishnu Naik
- Registered office
- Baba Sadan
- North
- Adj City Survey No 1702 1713
- South
- Adj City Survey No1715
- East
- Mumbai Goa Highaway
- West
- DP Road
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- SARASWAT COOPERATIVE BANK LIMITED โ 143313IFSC SRCB0000336Ground Floor Rameshwar Plaza Mumbai Goa highway Kankavli
Commencement Certificate documents
- COMMENCEMENT CERTIFICATE.pdf
Buyer community
Connect with other buyers and owners of Gangeshwar Plaza โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Gangeshwar Plaza. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.