SAI DARBAR
2502B, PILANKAR WADI, 416602
- Possession date passed. The proposed possession date (Oct 2023) has passed with construction at 72.7%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2023 per the RERA filing.
Official RERA facts
- Registration
- P52900033068
- Status
- New
- Stage
- Certificate Signed
- Possession
- October 2023
- Construction
- 72.7% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
KAILAS SATELKAR, SANDESH SAWANT
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Feb 2022
- Floors
- 3
- Plot / CTS / survey no.
- 2502B
- Planning authority
- Others
- Approved layout land
- 423.69 sq.m
- Land for this registration
- 423.69 sq.m
- Permissible built-up area
- 572.23 sq.m
- Promoter contact
- KAILAS SURESH SATELKAR
- Registered office
- NAIK COMPLEX
- North
- ROAD
- South
- 2503
- East
- ROAD
- West
- 2502A
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- BANK OF MAHARASHTRA โ 91365IFSC MAHB0001397JEEVAN TARA SANKUL
Commencement Certificate documents
- order_compressed.pdf
Buyer community
Connect with other buyers and owners of SAI DARBAR โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SAI DARBAR. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.