Nirman HeightsMahaRERA P52900053822
1641, 1642, 1643, 1644, 1647, 1648, 1649, 1650, 1651, Maruti Aali, 416602
- Possession delayed ~2 yrs. Originally promised Mar 2025, now proposed Dec 2026 per the RERA filing.
- Behind schedule. Possession is due Dec 2026 but construction is only at 43.6%.
Official RERA facts
- Registration
- P52900053822
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally March 2025
- Construction
- 43.6% complete
- Units sold
- 6 of 27
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
Manoj Narayan Thakur, Manisha Narayan Thakur, Meghana Abhishek karangutkar, Aditi Yogesh Dhuri, Anil Mohanrao Bhosale, Jayashree Devdatt Khambal, Kishori Mohanrao Bhosale, Kalyani Krishna Patil, Sandhya Satyavijay Rajput, Rekha Ramesh Pophae, Chandrakant Vishnu Thakur, Sushila Vishnu Thakur
Possession extension history
- EXT52900028005Revised to December 2026
I had completed my 90% project only 10% is left, even next month we r going to apply for Occupancy Certificate.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Dec 2023
- Floors
- 5
- Unit mix
- 12 res ยท 15 comm
- Architect
- Sanjay Andhari
- Plot / CTS / survey no.
- 1641, 1642, 1643, 1644, 1647, 1648, 1649, 1650, 1651
- Planning authority
- Kankavli Nagar Panchayat
- Approved layout land
- 787.5 sq.m
- Land for this registration
- 787.5 sq.m
- Permissible built-up area
- 1,208.65 sq.m
- Promoter contact
- Rohan Shashikant Ragaji
- Registered office
- Shraddha Shanti
- North
- Adj CTS 1652 1653
- South
- Road
- East
- Adj CTS 1640
- West
- Adj CTS 1645 1646
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- BANK OF INDIA โ 15468IFSC BKID0001466Morye Building Patwardhan Chowk Kankavli
Commencement Certificate documents
- Sanction Order.pdf
Buyer community
Connect with other buyers and owners of Nirman Heights โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Nirman Heights. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.