Under construction

ELIXA PARKMahaRERA P53000001735

by AJAYSINH V DESAI BUILDERS & DEVELOPERS

Plot No.A C.S.No. 517A/1, ‘E’ Ward, 416001

Jun 2025
Possession
86.2%
Built
0
Complaints
334
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2022, now proposed Jun 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 86.2%.

Official RERA facts

Registration
P53000001735
Status
Ongoing
Stage
Certificate Signed
Possession
June 2025originally December 2022
Construction
86.2% complete
Units sold
284 of 334

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths95%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting90%
Street Lighting80%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Jul 2017
Floors
20
Unit mix
202 res · 132 comm
Architect
A Square Mr Amar Upadhye

Buyer community

Connect with other buyers and owners of ELIXA PARK — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching ELIXA PARK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.