Under construction
HIRANYAKESHI COMPLEXMahaRERA P53000006212
148, Gijavane, 416502
Oct 2020
Possession
67.7%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Oct 2020 per the RERA filing.
- Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 67.7%.
Official RERA facts
- Registration
- P53000006212
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- October 2020originally December 2018
- Construction
- 67.7% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths25%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains25%
Landscaping & Tree Planting25%
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water70%
Water conservation /Rain water harvesting80%
Energy managemcntnot started
Electrical meter room, sub-station, receiving station50%
Building & registration
- RERA registered
- Aug 2017
- Floors
- 9
Buyer community
Connect with other buyers and owners of HIRANYAKESHI COMPLEX โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching HIRANYAKESHI COMPLEX. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.