HIRANYAKESHI COMPLEXMahaRERA P53000006212

by Vijay Ramchandra Godse

148, Gijavane, 416502

Oct 2020
Possession
67.7%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2018, now proposed Oct 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Oct 2020) has passed with construction at 67.7%.

Official RERA facts

Registration
P53000006212
Status
Ongoing
Stage
Certificate Signed
Possession
October 2020originally December 2018
Construction
67.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths25%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains25%
Landscaping & Tree Planting25%
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water70%
Water conservation /Rain water harvesting80%
Energy managemcntnot started
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Aug 2017
Floors
9

Buyer community

Connect with other buyers and owners of HIRANYAKESHI COMPLEX โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching HIRANYAKESHI COMPLEX. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.