SILVER OAK PHASE 2MahaRERA P53000025215
79/4,79/5/6/2,79/5/6/3, NEAR RELIANCE PETROL PUMP, 416502
- Possession date passed. The proposed possession date (Mar 2024) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P53000025215
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2024
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Landowner
VISHWANATH VIRBHADRAPPA PATTANSHETTI, BHASKAR RAMGONDA PATIL, ARUN LAXMAN TELANG, VIJAY BABURAO TELANG
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Mar 2020
- Floors
- 9
- Plot / CTS / survey no.
- 79/4,79/5/6/2,79/5/6/3
- Planning authority
- Others
- Approved layout land
- 4,808.5 sq.m
- Land for this registration
- 4,808.5 sq.m
- Recreational open space
- 480.85 sq.m
- Permissible built-up area
- 2,009.03 sq.m
- Promoter contact
- BHASKAR RAMGONDA PATIL
- Registered office
- OMKAR PRIDE 3
- North
- AJARA SANKESHWAR ROAD
- South
- NAGARPARISHAD ROAD
- East
- MUTTON MARKET
- West
- ATHARV APARTMENT
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- Bank not specifiedIFSC IDBI0001174GAT NO 76 BHADGAON ROAD GADHINGLAJ
Commencement Certificate documents
- Permission.pdf
- REWISE PERMISSION2021.pdf
Buyer community
Connect with other buyers and owners of SILVER OAK PHASE 2 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SILVER OAK PHASE 2. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.