πŸ—οΈ
Under construction

CLYDE HOMES phase2

MahaRERA P53000026035High risk

by VARAD DEVELOPERS

RS NO 209A/1 HISSA NO 1K/1 AND 1K/2, TARABAI PARK, 416003

Official record
Aug 2024
Possession
49.3%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Aug 2024) has passed with construction at 49.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Aug 2024 per the RERA filing.

Promoter

Builder profile

Builder
VARAD DEVELOPERS

View the promoter’s full developer profile and other projects under the same builder group.

Official RERA facts

Registration
P53000026035
Status
New
Stage
Certificate Signed
Possession
August 2024
Construction
49.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parking85%

Building & registration

RERA registered
Aug 2020
Floors
19
Plot / CTS / survey no.
RS NO 209A/1 HISSA NO 1K/1 AND 1K/2
Planning authority
Others
Approved layout land
3,720 sq.m
Land for this registration
3,720 sq.m
Permissible built-up area
14,040 sq.m
Registered office
Varad Residency
Plot boundaries
North
RS NO 208
South
12M WIDE
East
RS NO 209A1 HISSA NO 2
West
RS NO 209A1 HISSA NO 1K3 AND 1K5
Parking

Project bank account

The RERA-designated account this project's payments should go to β€” verify before wiring any money.

  • BANK OF BARODA β€” 10343
    IFSC BARB0TARABA
    SAYANTARA COMPLEX, E WARD, NAGALA PARK, KOLHAPUR

Commencement Certificate documents

  • COMMENCEMENT CERTIFICATE(1).pdf
  • commencement Certificate Clyde Homes C-Wing_compressed.pdf

Buyer community

Connect with other buyers and owners of CLYDE HOMES phase2 β€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet β€” start one and connect with the next buyer researching CLYDE HOMES phase2. Real notes from real buyers beat any brochure.

Start a discussion