MARK 1034
by Grey Bricks Real Estate And Infrastructure
CS no 1034, E Ward, 416001
- Possession delayed ~1 yr. Originally promised Jul 2025, now proposed Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P53000034142
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally July 2025
- Construction
- 90.9% complete
- Units sold
- 20 of 64
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Possession extension history
- EA23092502675Revised to December 2026
The work of the building is in progress; however, due to certain technical issues, only the backside ramp work is pending. Hence for the same project will not complete within stipulated time
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Mar 2022
- Floors
- 8
- Unit mix
- 14 res ยท 50 comm
- Architect
- Ar Pravin A Patil
- Plot / CTS / survey no.
- CS no 1034
- Planning authority
- KOLHAPUR MUNICIPAL CORPORATION
- Approved layout land
- 1,054 sq.m
- Land for this registration
- 1,054 sq.m
- Recreational open space
- 255 sq.m
- Permissible built-up area
- 2,913.1 sq.m
- Registered office
- Dwarka Residency
- North
- Cs no 1031
- South
- Municipal Corporation 15 mtr Main Road
- East
- Cs no 1035
- West
- CS no 1033
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- SARASWAT COOPERATIVE BANK LIMITED โ 143302IFSC SRCB0000309New Shahupuri, Kolhapur
Commencement Certificate documents
- Sanction Certificate PDF.pdf
Buyer community
Connect with other buyers and owners of MARK 1034 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MARK 1034. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.